太行改与四代试车时间相差1--年的困惑.

来源:百度文库 编辑:超级军网 时间:2024/04/29 13:43:10
]]
1995 Supporters contend that the F-22 can also be used in an air-to-ground role. However, the Congressional Budget Office concluded in a February 1995 report that the F-22's utility in this role would be far less than that of an aircraft designed specifically for that mission.  
The Congressional Budget Office report entitled "Reducing the Deficit" concluded in February 1995 that cancellation of the F-22 program would result in a five-year savings of $14.5 billion dollars. The CBO's primary reason for the cancellation option is that the F-22's additional capability is both unnecessary and too expensive.  

The Critical Design Review (CDR) of the F-22 and the Initial Production Readiness Review (IPRR) of the F119 engine were completed in February 1995. The Air Force confirmed that the program was ready to proceed to fabrication and assembly of EMD aircraft.  

Assembly work also begun at Fort Worth Summer 1995  

Assembly of forward fuselage launched at Marietta on 2 November 1995 with start of work on nose landing gear well;  

Supporters of the F-22 are expected to try and add $200 million to the military budget in fiscal year 1996 to avoid delays in the F-22 program. The Air Force originally requested $2.3 billion for fiscal year 1996 for the F-22 program, but the Pentagon reduced that to $2.1 billion. This follows a $110 million cut by Congress in the 1995 budget request, and $163 million in the FY 1994 budget plan.

February 24, 1995 The formal portion of the F-22 air vehicle Critical Design Review (CDR) is completed. A very small number of items remain open after this review, and these items are closed as scheduled by June. This thorough review of the F-22 air vehicle marks completion of the detailed design phase of the program and insures that the F-22 is ready to proceed into fabrication and assembly.
March 15, 1995 Lockheed Corporation and Martin Marietta complete a "merger of equals". New entity is named Lockheed Martin Corporation.
April 20, 1995 Air Force awards the Lockheed-Boeing team a $9.5 million, 24-month study contract to explore derivatives of the F-22 aircraft. P&W is awarded a separate $500,000 contract to explore improved F119 performance. The Air Force later curtails this study.
June 27, 1995 Assembly of the first flyable F-22 begins in Fort Worth.
Summer Wind tunnel testing of the F-22's configuration is completed. Twenty-three models were tested in 14 facilities in the U.S. and one in Germany during the 16,930 hour wind tunnel program that began in 1991.  
July 1995 Pratt & Whitney's redesigned F119 turbine demonstrates improved fuel efficiency and elimination of turbine blade vibratory stress.
October 4, 1995 Assembly of the first flyable F-22 begins at Boeing as workers load parts for the aft fuselage into an assembly fixture.
November 2, 1995 Assembly of the first flyable F-22 begins in Marietta as workers load parts for the nose landing ear wheel well into an assembly fixture.
1996 $2.15 billion has been requested for fiscal year 1996
Mating of three assemblies that comprise the mid-fuselage of first EMD aircraft taking place in Spring 1996  

Road transfer of the entire section to Marietta in August 1996, starting the final assembly process;  

The anticipated total program cost of the F-22 is $73.5 billion for 442 aircraft.  

January 17, 1996 Boeing begins assembly of the first shipset of wings for the first flyable F-22.
February 1996 Tests of the F-22's flight control laws begin in the Variable Stability In-flight Simulator Aircraft (VISTA), a highly modified, one-of-a-kind F-16D that, through a sophisticated control system, can emulate the flight characteristics of another airplane while in flight. These tests, which take place over upstate New York, are done in two sessions and are completed in May.  
May 6, 1996 Pratt & Whitney begins assembly of the first flight test F119 engine at its Middletown, CN, facilities.
July 9, 1996 Pratt & Whitney begins assembly of the first flight test F119 engine.
July 10, 1996 Air Force defers the requirement for design and development of the two seat F-22B. All (nine) of the EMD F-22s are now single seat models.
August 29, 1996 Lockheed Martin Tactical Aircraft Systems in Fort Worth holds a ceremony to commemorate completion of the mid fuselage for the first flyable F-22.
September 6, 1996 The mid fuselage for the first flyable F-22 (Ship 1) arrives in Marietta after a four-day truck trip from Lockheed Martin Tactical Aircraft Systems in Fort Worth, Tex. Forward-to-mid fuselage mate operations then begin.
September 24, 1996 Pratt & Whitney announces that the first flight test F119-PW-100 engine has been delivered to the Air Force. It will first taken to Arnold AFB, Tenn., for testing and then it will be delivered to Lockheed Martin in Marietta, Ga.  
October 1, 1996 Northrop Grumman (formerly Westinghouse) announces that the first developmental AN/APG-77, the electronically steered, active element, phased-array radar to be used in the F-22, begins system level integration and test.
October 8, 1996 First two flight test F119 engines are delivered to Marietta via truck.
October 16, 1996 Aft fuselage for the first flyable F-22 arrives in Marietta and mate operations begin. The aft fuselage was flown from Seattle on board a C-5 aircraft.
October 27, 1996 The completed fuselage of the first F-22, 4001, is lifted from the body mate tool to the wing mate tool.
November 9, 1996 The wings for 4001 arrive in Marietta and mate operations are completed two days later.
November 1996 Building L-64, Coatings/Finishes Building is completed. Also known as the "RCS" Building.
December 1996 Electrical power is applied to the F-22 for the first time.
1997 $2.05 billion requested for fiscal year 1997.  
First flight of an EMD aircraft, which was originally planned for May 1997 took place in September 1997.

Fall 1997
The number-one YF-22 prototype, painted and marked as the Pratt & Whitney powered aircraft, is scheduled to be put on display at the U. S. Air Force Museum at Wright-Patterson AFB, Ohio.   

October 1997
Approximately 10 F-22 test flights will be made from Marietta, Ga. During the later flights, the F-22 will undergo aerial refueling qualifications.  

Although the Navy would like to adopt a variant of the F-22, the current design is only capable from operating from long, land based air strips. This model does not have a strong enough frame to handle the violent jolts incurred from landing on a short, moving aircraft carrier deck. The Navy maintains the option to begin work on their own variant in 1997.

January 1997 The first F119 engine is fit checked into the 4001.
January 21, 1997 Left vertical stabilator is installed in 4001.
February 1997 Building B-22, engine noise attenuation facility (Hush House), is completed.
February 6, 1997 Right vertical stabilator is installed in 4001.
February 17, 1997 F119 engine endurance testing is completed.
March 6, 1997 4001, nearly complete, is towed from final assembly area in B-1 Building to newly constructed Hush House.
March 31, 1997 F119-PW-100 engine is granted Initial Flight Release.
April 9, 1997 Aircraft 4001 is publicly unveiled in rollout ceremonies at Marietta. During the ceremony, the fighter is christened with its official nickname -- Raptor.  
August 7, 1997 Weight Off Wheels (WOW) test completed.
August 16, 1997 Low speed taxi tests conducted.
August 25, 1997 Low speed (up to 60 knots) taxi tests accomplished.
September 3, 1997 Successful engine run completed.
September 4, 1997 Additional engine run to gather additional data points.
September 5, 1997 High speed taxi tests completed; after taxi, engines were inspected and found to be damage free.
September 7, 1997 Chief Test Pilot Paul Metz made the first flight of an EMD F-22 from Marietta, Ga.  
September 14, 1997 Second flight of 4001, piloted by Jon Beesley, F-22 test pilot from LMTAS. Primary objective was to gather data relative to the Environmental Control System (ECS) primary heat exchanger inlet performance. Shortly after takeoff, power to the data acquisition system was lost; remainder of the flight was devoted to familiarization with the aircraft handling qualities. Total flight time was 35 minutes.
September 16, 1997 Planned third flight cancelled due to failure of a hydraulic isolation valve, which would have precluded raising the landing gear during flight. Team and Air Force decided to stop this phase of flight test and prepare the airplane for transporting to Edwards for remainder of flight test.
November 7-13,1997 Gold Team led by General Al Slay reviews the F-22 Affordability Analysis - 1997/1998.
November 11, 1997 "Popular Science" magazine designated the F-22 as one of the "100 Best of What's New" for 1997. Awards are made annually to what the magazine considers top technology development programs. YF-22 program won a similar award in 1991.
November 13, 1997 Independent Cost Evaluation (ICE) team of corporate experts met in Marietta to provide the program and the corporation an independent assessment of costs associated with production.
December 4, 1997 Special team from F-22 Combined Test Force convened in Marietta develop plan and schedule for airlift of Aircraft 4001 to Edwards Air Force Base (EAFB) and restoration for subsequent flights at EAFB.
December 16, 1997 Affordability Analysis --1997/1998 (AA97/98) presented to Mrs. Darleen Druyun, Principal Deputy Assistant Secretary of the Air Force for Acquisition and Management.
December 19, 1997 AA97/98 presented to Air Force Chief of Staff. The analysis comprised production estimates for Lots 1 and 2, a target price curve for Lots 3-5 and the action plan to meet Air Force funding profile. Contractor CEOs and Air Force Chief of Staff agreed to accept a firm fixed price for Production Lots 1 and 2 for the budgeted amounts.
1998 March 31, An official ceremony today marked the transfer of the YF-22, the prototype for the F-22 Raptor, to the U. S. Air Force Museum at Wright-Patterson AFB, Ohio.
May 17~18, The F-22 added another page to the base's long history of aviation milestones today when it resumed active flight testing at approximately 7:30 in the morning at Edwards Airforce Base. One day later the aircraft continued to check out "Code One", mening returning to base with no deficiencies.

July 30, F-22 testers air-refueled a Raptor for the first time when aircraft 4001 topped off its tank behind a KC-135 about one-and-a-half hours into a test flight here July 30. The air refueling took place at an altitude of 20,000 feet and an air speed of 300 knots (approximately 345 mph) above Edwards Airforce Base.

August 26, The second US Air Force F-22 Raptor air dominance fighter, designated Raptor 4002, made its first cross-country flight today nonstop from Dobbins Air Reserve Base, Marietta, Ga., to Edwards Air Force Base, Calif. In California

October 13, Lockheed Martin test pilot Jon Beesley has flown the first F-22 built by Air Force contractors Lockheed Martin, Boeing, and Pratt & Whitney faster than the speed of sound for the first time.  

The Air Force plans to procure 438 production F-22s, and production is scheduled to run through 2013.

January 5, 1998 Air Force issued Request for Proposal for Low Rate Initial Production (LRIP) Lots 1 and 2 and LRIP Program Support. Response due March 16.
January 21, 1998 Government Accounting Office met in L-22 Conference Center for on-site review of Air Force Plant 6. Review is in response to the Authorization Bill requirement for annual GAO report (by March 15 each year) on F-22 program status.
January 23, 1998 Wings removed from 4001 this week and being prepared for shipment in wing crates salvaged from Boeings 4002 shipment to LMAS. 4001 is scheduled to be transported via C-5 to EAFB to begin preparation for EMD flight test.
February 4, 1998 Air Force C-5 arrived in Marietta to pick up Ship Serial 4001 for transport to Edwards Air Force Base.  
February 5, 1998 The C-5 with the F-22 on board departed Marietta just prior to noon today, 11 days ahead of scheduled February 16 departure.
February 25, 1998 The Honorable F. Whitten Peters, Acting Secretary of the Air Force, visited LMAS. Flew Concept Demonstrator.
March 16, 1998 F-22 Team delivered proposal volumes for Lots 1 and 2 and Program Support to System Program Office in Dayton, as planned. Cost volumes are scheduled for August delivery.
March 30, 1998 The 14-volume Affordability Analysis 1997/1998 was submitted to the SPO, one day ahead of scheduled submittal date.
March 31, 1998 In a formal ceremony, the YF-22 prototype aircraft was placed on public display at the Dayton Air Force Museum. F-22 SPO Director Brigadier General Mike Mushala signed over the aircraft documents to the museum.  
April 6, 1998 LM Aeronautical Sector President Micky Blackwell and Tom Burbage met with Principal Deputy Assistant Secretary of the Air Force Mrs. Darleen Druyun to discuss the Production Target Price Curve (TPC). They reached agreement on a revised TPC satisfactory to Lockheed Martin and the Air Force.
April 17, 1998 Aircraft 4002 moved to L-10 Building at Flight Line.
April 22, 1998 Auxiliary power unit runs began at Edwards on reassembled aircraft 4001.
May 12, 1998 Test Team at Edwards completed 30 and 60-knot taxi tests.
May 15, 1998 High-speed taxi testing completed on 4001at EAFB.
May 17, 1998 Lt. Colonel Steve Rainey piloted Raptor 01 (Ship 4001) in 1.2 hour flight (flight Number 3), marking beginning of EMD formal flight test. Test objectives were flying qualities envelope expansion, speed brake handling qualities, and formation flying qualities. All test points were flown precisely as briefed and the flight was a successful test mission.
May 20, 1998 Initial engine runs successfully conducted on 4002.
May 29, 1998 Flight Number 4 of aircraft 4001 at Edwards, 1.0 hours with Paul Metz in the cockpit.
June 1, 1998 Major General Claude M. Bolton, Jr., replaced Lt. General Bob Raggio as Program Executive Officer -- Fighters and Bombers.
June 19, 1998 Mrs. Darleen Druyun at Marietta for F-22 program review.
June 29, 1998 Aircraft 4002 initial flight at Marietta, scheduled 7-9-98, ten days early. Paul Metz was the pilot.
July 2, 1998 Government signed contract for two Production Readiness Test Vehicles (PRTV) and a separate contract for related program support. Production contract includes options for PRTV full award in December 1998, Advance Procurement for six Lot 1 Production aircraft in December 1998, and Lot 1 full award of Production aircraft in December 1999. The Program Support Contract includes options for program support to correspond with full award on PRTV and Lot 1.  
July 30, 1998 Aircraft 4001 in-flight refueling at 20,000 feet, 300 knots (pilot ñ Lt. Col. Steve Rainey).
August 4, 1998 Aircraft 4001 completed aerial refueling qualification at 30,000 ft, 300 KCAS. Pilot -- Jon Beesley.
August 12, 1998 Satellite media tour at Marietta. Media reporters across the United States call in via satellite and conduct live interviews with test pilots Chick Killberg (Boeing), Jon Beesley (LMTAS) and Lt. Colonel Steve Rainey (USAF).
August 23, 1998 USAF pilot Lt. Colonel Steve Rainey flew 4002 in an aerial refueled endurance flight of 4.6 hours.
August 26, 1998 Lt. Colonel Steve Rainey piloted Aircraft 4002 in the 4.5-hour ferry flight to Edwards Air Force Base. The aircraft was accompanied by two KC-135 tankers and an F-15 and F-16 chase plane piloted by Paul Metz and Jon Beesley, respectively. As Raptor 02 neared EAFB, the Test Team sent 4001 on its scheduled test flight so both F-22s were aloft at the same time, the first time this event has occurred.
August 31, 1998 An era in the F-22 program ended today as Don Herring transitioned from 11 years of guiding the program to assume duties as LMAS Vice President of Engineering.
October 1, 1998 The "Don Herring IPT of the Quarter" award is established by adding Don Herring to the award title. The Airworthiness and Delivery Team led by Vinny Devino was winner of the first renamed honor.
October 3, 1998 Aircraft 4002 was on static display at the air show at Edwards Air Force Base. Reports indicate the airplane was the most popular exhibit at the show. This was the first time one of the Raptors has been on public display.
October 10, 1998 Lockheed Martin test pilot Jon Beesley broke the sound barrier in aircraft 4001 during a 2.8-hour flight that reached speed of 1.1 Mach. When the Raptor 4001 reached Mach speed it was flying in the skies over Edwards Air Force Base at an altitude of 29,000 feet at approximately 3:25 p.m. Pacific Daylight Time. Total flight time on this aircraft is 45.0 hours; supersonic time is approximately 20 minutes.
November 12, 1998 Avionics Software Manager (ASM) final Block 2 Critical Design Review (CDR) was held one week early.  
November 23, 1998 The first Block 1 integrated production software was released to the Flying Test Bed (FTB) 2 weeks early.
November 23, 1998 Lockheed Martin met the congressionally-mandated 183 flight hour mark more than a month ahead of schedule and three days before a target date set my Air Force Chief of Staff General Michael Ryan.
December 28, 1998 The Air Force exercised a firm fixed price contract option with Lockheed Martin totaling approximately $503 million for two F-22 production representative test vehicle (PRTV) aircraft and associated program support for calendar year 1999. The PRTVV deliveries are scheduled to commence in November 2001 and continue through January 2002.
December 30, 1998 Lockheed Martin received a firm fixed price contract option for the advance procurement of six Low Rate Initial Production (LRIP) aircraft totaling approximately $189 million.
1999 The final Production Readiness Review for the F119 engine is scheduled to take place at Pratt & Whitney's facility in West Palm Beach, Fla. Later in the month, the F119 Full Flight Release is scheduled to be granted. Due to happen mid 1999  
First flight of an EMD F-22 with a full avionics suite is expected to take place around mid 1999

September 30, 1999
The last of 27 EMD F119 flight test engines are scheduled to be delivered to Lockheed Martin Aeronautical Systems.  

Low-rate initial production is scheduled to begin in 1999.

Planned delivery of lot 1: 2 pcs  

During July the House Appropriations Committee agreed to suspend planned production of the F-22 stealth fighter, taking away some $1.8 billion in production funds to buy the first six fighters from Lockheed Martin Corp

Frantic negociations were held over the next few months, to reach an agreement before the next fical year started october 1st '99. House and Senate negotiators ended the struggle, giving the Air Force only half the $1.8 billion it had requested for next year to get the F-22 off the ground. The compromise spared the $65 billion program from being scrapped, as the House had voted last July.  

The planes could only be put into production if certain performance tests were passed.

January 12, 1999 A new MiG fighter jet, conceived as a Russian response to the U.S. combat aircraft was unveiled. The Multi-Functional Fighter, known as "Project 1.42" in the West, is proclaimed by the MAPO-MiG company that produces it, to be able to outperform the F-22 Raptor.
2000 Planned delivery of lot 2: 6 pcs
Early 2000 The Air Force is scheduled to award the Lot 2 production contract. These six F-22s are to be delivered in 2002.  
2001 The contractor portion of the Engineering and Manufacturing Development (EMD) phase of the program is scheduled to be completed.  
Planned delivery: ? pcs

Early 2001 The Air Force is scheduled to award the Lot 3 production contract. These 12 F-22s are to be delivered in 2003.
Mid 2001 The last of the nine F-22s to be built during the Engineering and Manufacturing Development (EMD) phase of the program is scheduled to be delivered to the Air Force.  
Early 2002 The contractor portion of the Engineering and Manufacturing Development (EMD) phase of the program is scheduled to be completed.
Early 2002 The Air Force is scheduled to award the Lot 4 production contract. These 20 F-22s are to be delivered starting in late 2003 and running through 2004.
Early 2003 The Air Force's Dedicated Initial Operational Test and Evaluation (IOT&E) program is scheduled to be completed, thus officially ending the Engineering and Manufacturing Development (EMD) phase of the F-22 program.
Early 2003 The Air Force is scheduled to award the Lot 5 production contract. These 30 F-22s are to be delivered starting in late 2004 and running through 2005
2004 The F-22 is scheduled to enter operational service and it will begin to take over the air dominance role first with Air Combat Command late 2004.  
Planned delivery: ? pcs

Early 2004 The high-rate production decision for the F-22 is expected to be made by the Air Force. This Lot 6 contract will cover 48 aircraft. These F-22s will be delivered in late 2005 and 2006.
Late 2004 The F-22 is scheduled to enter operational service.
2013 The last of the 339 production F-22 aircraft currently planned for the Air Force is scheduled to be delivered.
看米国四代的发动机研制路程,F119起初最大速度只有1.8M,超巡只能到1.58M,
1995年4月20, 批钱改进F-119的性能.
1995年7月又重新设计涡轮提高燃油效率改进叶片振动缺陷..
]]
太行改02年就试车了,四代才刚总装吧,10~12能上高空台就不错了,"2012四代首飞".....前提是毛鳖四代2011首飞....."2015定型".....这个只能靠撸了......
2003,F-22的EMD阶段完成,进入批产.....
原帖由 MinstrelBoy 于 2008-3-12 13:36 发表
太行改02年就试车了,四代才刚总装吧,10~12能上高空台就不错了,"2012四代首飞".....前提是毛鳖四代2011首飞....."2015定型".....这个只能靠撸了......

你说的哪个太行改,偶说的这个今年试车的不是02年开始的,看张恩和言论是06年开始工程制造的....
]]
米国的航发不是一般的强!
]]